With the construction start date set for this spring, Cullman officials nailed down some financing specifics and discussed the pending land acquisition process for the Duck River dam project this week.
The Cullman Utilities Board currently plans to take out a $50 million bond for the first phase of the approximately $68 million project in the coming months, then fund the remainder via another bond in approximately two years. Officials hope to go out to the bond market by late May, according to a schedule released at a Monday meeting.
The exact amount of the second bond is not yet known, as officials hope to acquire federal funding for the project in the coming years to offset some of the cost.
Tom Harwell, with engineer of record CH2M Hill, said the bond report for the project is currently being written. The report, which will be pitched to investors, includes estimates of how water rates will change once the project is complete, and potential needs within the next 5-10 years. To pay back the bonds, wholesale water rates are slated to increase by approximately 59 percent — from $1.50 per 1,000 gallons this year to around $2.57 by 2016.
The effect growth would have on the system is also noted in the report, and states up to $14 million in potential upgrades and expansions could be needed at the city water treatment plant in the next five years if the system adds additional customers or witnesses a population boom.
“What that means is if the growth warrants it, it doesn’t mean you’re locked in to do it,” Harwell said. “It just shows there is a plan in place if it is needed.”
City council president Garlan Gudger, Jr., a member of the utilities board, clarified the report does not bind the council to make any upgrades, but instead provides a basic framework.
“The authority still rests with this board,” he said. “If we decided to do it, we can do it, but if not, then we won’t.”
Project liaison Dale Greer updated the board on his recent trip to Washington, D.C., on March 15-16 where he met with legislators in an effort to attain federal grants for the dam project. The board has applied for federal dollars in years past, though environmental lawsuits over the last decade delayed the project from starting. Now, in the midst of an economic recession, Greer noted that many of those sources have begun to dry up.
“We had some very positive meetings, and they were really pleased that all of the water systems are on board now,” he said. “But, they basically implied we’re two years away from being able to get any money.”
Property acquisition for the 89 landowner parcels within the watershed is scheduled to take place within the next four weeks, and land acquisition coordinator Mandell Tillman said he needs to be able to act quickly to close land purchases to keep the project on schedule, once appraisals and review appraisals are complete. To that end, the board approved chairman Wayne Fuller, board member Johnny Cook and the rest of the board’s finance committee to approve offers that arise between scheduled board meetings.
“We can’t make an offer until that price is approved by the board, so this would help streamline the process,” Tillman said. “But, relocations could hold up the negotiations, because there is a 90 day federal guideline after the initial offer is made. That’s where we could potentially be held up, and why it’s so important to get this going now.”
A potential cost-savings measure was discussed by owner’s representative Bill St. John, an engineer hired earlier this year by the utilities board. St. John said reworking the pipeline path down the U.S. Hwy. 278 right of way and around some county roads could make the process much simpler — reducing the amount of landowners affected from around 50 to five.
“We met with county commissioner (Darrell) Hicks and road superintendent Roy Jackson, and talked about using county roads to put the pipeline in, and had a really good meeting with them, and that should help keep us out of some private property easements and make that a lot easier,” he said. “That is a huge help, with the county being willing to do that.”
Once the Duck River dam is complete, the water source project will encompass a 640-acre lake with a 32-million-gallon-per-day capacity, and a six-mile pipeline. The reservoir will be located in the northeast portion of the county, east of Lake Catoma.
* Trent Moore can be reached by e-mail at trentm@cullmantimes.com, or by telephone at 734-2131, ext. 220.
Top News
Duck River financing, plans in the works
- Top News
-
-
Woman charged with torture, abuse of a child
A Cullman County woman was arrested by sheriff's deputies over the weekend after here 14-year-old son was beaten in the front yard of their home.
-
Smith Farms Music Fest picks up in second night (WITH PHOTO GALLERY)
The opening night of the first ever Smith Farms Music Festival may have attracted a slightly smaller than anticipated crowd Thursday, but event organizer Rodger Turner said those who came out definitely got their money’s worth.
-
Chamber President Kirk Mancer resigns
Cullman Area Chamber of Commerce President Kirk Mancer has resigned to take a similar position with the Greater Shelby County Chamber of Commerce.
-
Look for a hot Memorial Day weekend
Hot.
That's the only word needed to describe the weather for the Memorial Day weekend. -
Arrests, incident reports for Thursday, May 24
Here is a look at the incidents that were reported to the Cullman Police Department for Thursday:
-
County commission move to clean up storm-damaged waterways
The Cullman County Commission will go forward in a partnership with the U.S. Department of Agriculture to rehabilitate several streams throughout the county clogged by vegetative debris created by last April’s storms.
-
Case of Baileyton man accused of stabbing wife to death sent to grand jury
A grand jury will now hear the case of a Baileyton man accused of murdering his wife in March.
- Arrests, incident reports for Wednesday, May 23
-
Authorities investigating counterfeit money
Local authorities and the U.S. Secret Service are on the lookout for two people who passed a $100 counterfeit bill at Steele Orchard Wednesday.
-
Cullman Christian School celebrates inaugural graduation ceremony (WITH PHOTO GALLERIES)
To call the past year a hard one for Cullman Christian School would be an understatement. The school’s original facility at East Side Baptist Church was destroyed in the April 27, 2011 tornadoes, and plans to build a new campus are stalled due to a zoning dispute with the City of Cullman.
- More Top News Headlines
-


